30” Q-Model Water/Remote Insulation
Installation Instructions
Material List Q-0280 - Q-1000 Water and Remote Ice Machines:
Quantity
1
1
Armaflex Insulation
Armaflex Insulation
6’ x 2” ID x 3/8” wall thickness
6’ x 3/4” ID x 3/8” wall
(used on evaporator inlet/outlet and dump valve drain line)
1
1
2
1
1
1
1
1
Bulkhead Insulation Back
Bulkhead Insulation Back
Side Wall Insulation
Vacuum Formed Base with Insulation
Foam Gasket For Top Edge of Bin
Tube Silicone Sealant Black
Tube Silicone Sealant White
Mylar Strip
9” x 30” x 3/4”
3” x 30” x 3/8”
9” x 10” x 3/4”
12 3/4” x 30” x 3/4"
2’ x 3/4” x 1/4”
Used to seal base/bulkhead insulation
Used to seal front edge of vacuum-formed base
5” x 25”
Additional materials required: caulk gun, 2” x 4” wood blocks, wire ties.
Preparation
1. Disconnect power from ice machine.
2. Remove front, top, and side panels.
3. Drain water from sump trough.
4. Ice machine must be thoroughly dried before the insulation can be installed. Use towels to dry bulkhead and base assembly.
Base Insulation Installation
1. Raise the ice machine above the bin. A high lift can be used or (two people required) lift front edge of ice machine and place
wood blocks (2” x 4”) between ice machine and bin. Lifting one side of ice machine at a time, move wood blocks to center
balance point of ice machine.
2. Slide vacuum-formed base insulation assembly between the ice machine and bin. Align the insulation with the back and sides of
the bin and ice machine.
3. Add one layer of foam tape insulation from the front of the bin to the front of the base insulation on the left and right side.
2. Install vacuum-formed base
insulation and align back and sides.
3. Add foam tape both sides.
Manitowoc Ice, Inc.
2110 South 26 Street, P.O. Box 1720, Manitowoc, WI 54221-1720 USA
Telephone 920-682-0161, Fax - Sales: 920-683-7589, Service/Parts: 920-683-7585, Other: 920-683-7879
Web Site - www.manitowocice.com
8005493
Sheet 1 of 3
06/02/00
4. Raise front of ice machine and position the wood blocks on edge (3 1/2” height). This will allow the top of the vacuum-formed
base to be accessed.
9. Install additional insulation on entire suction
line
4. Apply bead of silicone before applying insulation
5. Align insulation slits with base ribbing
7. Seal insulation to base with silicone sealant
10. Insulate drain line
5. When installing in limited access areas, the insulation can be cut to allow installation of the bulkhead insulation in two pieces.
Peel the white backing off of the insulation for the back bulkhead (9” x 30”). Align the slots in the insulation with the ridges in
the base. Press the insulation against the bulkhead to secure. The insulation will overlap the left and right side insulation
installed earlier. Ensure that the foam and fiberglass insulation mates flush with no voids.
6. Peel the white backing off of the 3” x 30” strip of insulation and install over the bottom section of the 9” x 30” insulation
installed in step 6. Align cut slots with the back bulkhead insulation and press to seal.
7. Use black silicone sealant to seal: insulation to the base, foam insulation to foam insulation joints, any voids where insulation
meets or overlaps. Add bulkhead corner insulation covers where the rear bulkhead and side panel corners meet.
8. Verify no moisture is present in the suction line tubing. If moisture is present, drain and dry the insulation and reinstall
following step 10 instructions.
9. Install armaflex insulation over the existing insulation on suction line. Use 3/4” x 3/8” insulation on the evaporator outlet and
inlet tubing and 2” x 3/8” on the rest of the suction line. Use suitable glue to seal insulation airtight (do not use electrical tape).
Seal the ends of the insulation with wire ties.
10. Remove clear vinyl tube from dump valve and brass wing adapter. Install armaflex insulation over tube and then reinstall tube
to dump valve and adapter. Ensure white clamps are secure to prevent water from leaking.
8005493
Sheet 3 of 3
06/02/00
|